Cra 25 # 22c-34 Barrio Samper Mendoza

Oil & Gas

Projectdetail

  • Project completion date

    April 2021.

  • Service

    Power Quality

  • Category:

    Companies

Brief description of the project:

Diagnosis and corrective maintenance of thirty-two (32) Active Filters of the Schneider Electric PCS series installed in the CPF1 and CPF2 Crude Oil Production Facility Centers of Oil & Gas company

Benefits :

Before the service, there were 22 active filters out of service, once the diagnosis and corrective maintenance were done, the operation of 12 filters were recovered, leaving a total of 22 filters in service and only 10 out of service for change of spare parts and/or update. This made possible the considerably reduction of the reactive power consumption and the harmonic content present in the CPF1 and CPF2 systems, improving the electrical conditions of the equipment.

Technologiesused

Specialized equipment and tools for maintenance of Active Filters of the Schneider Electric PCS series.